{"id":"https://openalex.org/W3003326629","doi":"https://doi.org/10.1109/ieem44572.2019.8978524","title":"A Lazy-Constraints Approach to Resource-Constrained Project Scheduling","display_name":"A Lazy-Constraints Approach to Resource-Constrained Project Scheduling","publication_year":2019,"publication_date":"2019-12-01","ids":{"openalex":"https://openalex.org/W3003326629","doi":"https://doi.org/10.1109/ieem44572.2019.8978524","mag":"3003326629"},"language":"en","primary_location":{"id":"doi:10.1109/ieem44572.2019.8978524","is_oa":false,"landing_page_url":"https://doi.org/10.1109/ieem44572.2019.8978524","pdf_url":null,"source":null,"license":null,"license_id":null,"version":"publishedVersion","is_accepted":true,"is_published":true,"raw_source_name":"2019 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM)","raw_type":"proceedings-article"},"type":"article","indexed_in":["crossref"],"open_access":{"is_oa":false,"oa_status":"closed","oa_url":null,"any_repository_has_fulltext":false},"authorships":[{"author_position":"first","author":{"id":"https://openalex.org/A5085128266","display_name":"D. Lerch","orcid":null},"institutions":[{"id":"https://openalex.org/I118564535","display_name":"University of Bern","ror":"https://ror.org/02k7v4d05","country_code":"CH","type":"education","lineage":["https://openalex.org/I118564535"]}],"countries":["CH"],"is_corresponding":true,"raw_author_name":"D. Lerch","raw_affiliation_strings":["University of Bern,Department of Business Administration,Switzerland","Department of Business Administration, University of Bern, Switzerland"],"affiliations":[{"raw_affiliation_string":"University of Bern,Department of Business Administration,Switzerland","institution_ids":["https://openalex.org/I118564535"]},{"raw_affiliation_string":"Department of Business Administration, University of Bern, Switzerland","institution_ids":["https://openalex.org/I118564535"]}]},{"author_position":"last","author":{"id":"https://openalex.org/A5063630096","display_name":"\u039d. Trautmann","orcid":"https://orcid.org/0000-0003-0951-6567"},"institutions":[{"id":"https://openalex.org/I118564535","display_name":"University of Bern","ror":"https://ror.org/02k7v4d05","country_code":"CH","type":"education","lineage":["https://openalex.org/I118564535"]}],"countries":["CH"],"is_corresponding":false,"raw_author_name":"N. Trautmann","raw_affiliation_strings":["University of Bern,Department of Business Administration,Switzerland","Department of Business Administration, University of Bern, Switzerland"],"affiliations":[{"raw_affiliation_string":"University of Bern,Department of Business Administration,Switzerland","institution_ids":["https://openalex.org/I118564535"]},{"raw_affiliation_string":"Department of Business Administration, University of Bern, Switzerland","institution_ids":["https://openalex.org/I118564535"]}]}],"institutions":[],"countries_distinct_count":1,"institutions_distinct_count":2,"corresponding_author_ids":["https://openalex.org/A5085128266"],"corresponding_institution_ids":["https://openalex.org/I118564535"],"apc_list":null,"apc_paid":null,"fwci":0.2062,"has_fulltext":false,"cited_by_count":2,"citation_normalized_percentile":{"value":0.62918786,"is_in_top_1_percent":false,"is_in_top_10_percent":false},"cited_by_percentile_year":{"min":89,"max":94},"biblio":{"volume":null,"issue":null,"first_page":"144","last_page":"148"},"is_retracted":false,"is_paratext":false,"is_xpac":false,"primary_topic":{"id":"https://openalex.org/T12177","display_name":"Resource-Constrained Project Scheduling","score":0.9998999834060669,"subfield":{"id":"https://openalex.org/subfields/1803","display_name":"Management Science and Operations Research"},"field":{"id":"https://openalex.org/fields/18","display_name":"Decision Sciences"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}},"topics":[{"id":"https://openalex.org/T12177","display_name":"Resource-Constrained Project Scheduling","score":0.9998999834060669,"subfield":{"id":"https://openalex.org/subfields/1803","display_name":"Management Science and Operations Research"},"field":{"id":"https://openalex.org/fields/18","display_name":"Decision Sciences"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}},{"id":"https://openalex.org/T10551","display_name":"Scheduling and Optimization Algorithms","score":0.9869999885559082,"subfield":{"id":"https://openalex.org/subfields/2209","display_name":"Industrial and Manufacturing Engineering"},"field":{"id":"https://openalex.org/fields/22","display_name":"Engineering"},"domain":{"id":"https://openalex.org/domains/3","display_name":"Physical Sciences"}},{"id":"https://openalex.org/T13886","display_name":"Operations Management Techniques","score":0.968500018119812,"subfield":{"id":"https://openalex.org/subfields/1803","display_name":"Management Science and Operations Research"},"field":{"id":"https://openalex.org/fields/18","display_name":"Decision Sciences"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}}],"keywords":[{"id":"https://openalex.org/keywords/computer-science","display_name":"Computer science","score":0.7919334173202515},{"id":"https://openalex.org/keywords/scheduling","display_name":"Scheduling (production processes)","score":0.5692597031593323},{"id":"https://openalex.org/keywords/processor-scheduling","display_name":"Processor scheduling","score":0.5121133327484131},{"id":"https://openalex.org/keywords/distributed-computing","display_name":"Distributed computing","score":0.4273204207420349},{"id":"https://openalex.org/keywords/resource","display_name":"Resource (disambiguation)","score":0.36423546075820923},{"id":"https://openalex.org/keywords/mathematical-optimization","display_name":"Mathematical optimization","score":0.20933517813682556},{"id":"https://openalex.org/keywords/computer-network","display_name":"Computer network","score":0.10296660661697388},{"id":"https://openalex.org/keywords/mathematics","display_name":"Mathematics","score":0.06881323456764221}],"concepts":[{"id":"https://openalex.org/C41008148","wikidata":"https://www.wikidata.org/wiki/Q21198","display_name":"Computer science","level":0,"score":0.7919334173202515},{"id":"https://openalex.org/C206729178","wikidata":"https://www.wikidata.org/wiki/Q2271896","display_name":"Scheduling (production processes)","level":2,"score":0.5692597031593323},{"id":"https://openalex.org/C2984822820","wikidata":"https://www.wikidata.org/wiki/Q1123036","display_name":"Processor scheduling","level":3,"score":0.5121133327484131},{"id":"https://openalex.org/C120314980","wikidata":"https://www.wikidata.org/wiki/Q180634","display_name":"Distributed computing","level":1,"score":0.4273204207420349},{"id":"https://openalex.org/C206345919","wikidata":"https://www.wikidata.org/wiki/Q20380951","display_name":"Resource (disambiguation)","level":2,"score":0.36423546075820923},{"id":"https://openalex.org/C126255220","wikidata":"https://www.wikidata.org/wiki/Q141495","display_name":"Mathematical optimization","level":1,"score":0.20933517813682556},{"id":"https://openalex.org/C31258907","wikidata":"https://www.wikidata.org/wiki/Q1301371","display_name":"Computer network","level":1,"score":0.10296660661697388},{"id":"https://openalex.org/C33923547","wikidata":"https://www.wikidata.org/wiki/Q395","display_name":"Mathematics","level":0,"score":0.06881323456764221}],"mesh":[],"locations_count":2,"locations":[{"id":"doi:10.1109/ieem44572.2019.8978524","is_oa":false,"landing_page_url":"https://doi.org/10.1109/ieem44572.2019.8978524","pdf_url":null,"source":null,"license":null,"license_id":null,"version":"publishedVersion","is_accepted":true,"is_published":true,"raw_source_name":"2019 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM)","raw_type":"proceedings-article"},{"id":"pmh:oai:boris.unibe.ch:138877","is_oa":false,"landing_page_url":"https://boris.unibe.ch/138877/","pdf_url":null,"source":{"id":"https://openalex.org/S4306401086","display_name":"Bern Open Repository and Information System (University of Bern)","issn_l":null,"issn":null,"is_oa":false,"is_in_doaj":false,"is_core":false,"host_organization":"https://openalex.org/I118564535","host_organization_name":"University of Bern","host_organization_lineage":["https://openalex.org/I118564535"],"host_organization_lineage_names":[],"type":"repository"},"license":null,"license_id":null,"version":"submittedVersion","is_accepted":false,"is_published":false,"raw_source_name":"Lerch, Dennis; Trautmann, Norbert (16 December 2019). A Lazy-Constraints Approach to Resource-Constrained Project Scheduling. In: IEEEInternational Conference on Industrial Engineering and Engineering Management (IEEM). Macau. 15.-18.12.2019.","raw_type":"info:eu-repo/semantics/conferenceObject"}],"best_oa_location":null,"sustainable_development_goals":[{"display_name":"Reduced inequalities","id":"https://metadata.un.org/sdg/10","score":0.7400000095367432}],"awards":[],"funders":[],"has_content":{"pdf":false,"grobid_xml":false},"content_urls":null,"referenced_works_count":12,"referenced_works":["https://openalex.org/W32150173","https://openalex.org/W1564518751","https://openalex.org/W1973131489","https://openalex.org/W2024237395","https://openalex.org/W2036112575","https://openalex.org/W2053931030","https://openalex.org/W2153864093","https://openalex.org/W2753576362","https://openalex.org/W2786743500","https://openalex.org/W2907188437","https://openalex.org/W2965350733","https://openalex.org/W3150323996"],"related_works":["https://openalex.org/W2748952813","https://openalex.org/W2128410848","https://openalex.org/W2102390841","https://openalex.org/W2118368532","https://openalex.org/W2126232624","https://openalex.org/W2434525066","https://openalex.org/W3140149227","https://openalex.org/W2096289371","https://openalex.org/W2130555437","https://openalex.org/W3023290810"],"abstract_inverted_index":{"We":[0,78,114],"study":[1],"the":[2,9,16,20,23,30,37,44,57,90,104,108,121,133,143,154,157,162,167,171,178],"complex":[3,71],"combinatorial":[4],"optimization":[5],"problem":[6],"to":[7,18,52,72,103,116,152,176],"schedule":[8],"activities":[10,45,100],"of":[11,26,43,99,107,139,156,173],"a":[12,80,137],"single":[13],"project":[14,21,158],"with":[15,150],"objective":[17],"complete":[19],"within":[22],"shortest-possible":[24],"amount":[25],"time":[27],"such":[28],"that":[29,149],"limited":[31,105],"resource":[32],"capacities":[33,106],"as":[34,36],"well":[35],"prescribed":[38],"precedence":[39],"relations":[40],"between":[41],"pairs":[42],"are":[46,93,130],"taken":[47],"into":[48],"account.":[49],"In":[50],"addition":[51],"various":[53],"specific":[54],"solution":[55],"algorithms,":[56],"related":[58],"literature":[59],"proposes":[60],"several":[61],"Mixed-Integer":[62],"Linear":[63],"Programming":[64],"(MILP)":[65],"models,":[66],"but":[67],"these":[68,118],"models":[69],"remain":[70],"solve":[73],"even":[74],"for":[75,95],"small-sized":[76],"instances.":[77],"present":[79],"novel":[81,179],"approach":[82,181],"based":[83],"on":[84],"an":[85],"MILP":[86,185],"model":[87,122],"in":[88,132],"which":[89,129],"resource-capacity":[91],"constraints":[92,119,127],"formulated":[94],"all":[96],"inclusion-minimal":[97],"sets":[98],"which,":[101],"due":[102],"resources,":[109],"cannot":[110],"be":[111],"processed":[112],"simultaneously.":[113],"propose":[115],"remove":[117],"from":[120,142,161,166],"and":[123,170],"iteratively":[124],"add":[125],"those":[126],"back":[128],"violated":[131],"solutions":[134],"obtained.":[135],"For":[136],"set":[138],"test":[140],"instances":[141,174],"literature,":[144],"our":[145],"computational":[146],"results":[147],"indicate":[148],"respect":[151],"both,":[153],"deviation":[155],"duration":[159],"obtained":[160],"lower":[163],"bound":[164],"devised":[165],"critical-path":[168],"length":[169],"number":[172],"solved":[175],"optimality,":[177],"lazy-constraints":[180],"outperforms":[182],"ten":[183],"state-of-the-art":[184],"models.":[186]},"counts_by_year":[{"year":2023,"cited_by_count":1},{"year":2020,"cited_by_count":1}],"updated_date":"2026-04-05T17:49:38.594831","created_date":"2025-10-10T00:00:00"}