{"id":"https://openalex.org/W7203738017","doi":"https://doi.org/10.55606/jtmei.v5i3.6386","title":"Perencanaan dan Pengendalian Jadwal Proyek Fiber To The Home Menggunakan Metode Program Evaluation and Review Technique dan Metode Predence Diagram Method di PT XYZ","display_name":"Perencanaan dan Pengendalian Jadwal Proyek Fiber To The Home Menggunakan Metode Program Evaluation and Review Technique dan Metode Predence Diagram Method di PT XYZ","publication_year":2026,"publication_date":"2026-07-07","ids":{"openalex":"https://openalex.org/W7203738017","doi":"https://doi.org/10.55606/jtmei.v5i3.6386"},"language":"en","primary_location":{"id":"doi:10.55606/jtmei.v5i3.6386","doi":"https://doi.org/10.55606/jtmei.v5i3.6386","is_oa":true,"landing_page_url":"https://doi.org/10.55606/jtmei.v5i3.6386","pdf_url":null,"source":{"id":"https://openalex.org/S4387284260","display_name":"JURNAL TEKNIK MESIN INDUSTRI ELEKTRO DAN INFORMATIKA","issn_l":"2963-7805","issn":["2963-7805","2963-8208"],"is_oa":false,"is_in_doaj":false,"is_core":false,"listed_in":[],"host_organization":null,"host_organization_name":null,"host_organization_lineage":[],"host_organization_lineage_names":[],"type":"journal"},"license":"cc-by-sa","license_id":"https://openalex.org/licenses/cc-by-sa","version":"publishedVersion","is_accepted":true,"is_published":true,"raw_source_name":"Jurnal Teknik Mesin, Industri, Elektro dan Informatika","raw_type":"journal-article"},"parent_works":[],"lineage":["https://openalex.org/W7203738017"],"child_works_count":0,"type":"article","is_traditional":true,"indexed_in":["crossref"],"open_access":{"is_oa":true,"oa_status":"hybrid","oa_url":"https://doi.org/10.55606/jtmei.v5i3.6386","any_repository_has_fulltext":false},"authorships":[{"author_position":"first","author":{"id":"https://openalex.org/A5122208843","display_name":"Fauziah Nurcahya","orcid":null,"observed_orcids":[]},"institutions":[{"id":"https://openalex.org/I4210167078","display_name":"Universitas Widyatama","ror":"https://ror.org/05v27w196","country_code":"ID","type":"education","lineage":["https://openalex.org/I4210167078"]}],"countries":["ID"],"is_corresponding":false,"raw_author_name":"Fauziah Nurcahya","raw_affiliation_strings":["Universitas Widyatama Bandung"],"raw_orcid":null,"affiliations":[{"raw_affiliation_string":"Universitas Widyatama Bandung","institution_ids":["https://openalex.org/I4210167078"]}]},{"author_position":"last","author":{"id":"https://openalex.org/A5085030246","display_name":"Arief Rahmana","orcid":"https://orcid.org/0000-0002-8257-5814","observed_orcids":["https://orcid.org/0000-0002-8257-5814"]},"institutions":[{"id":"https://openalex.org/I4210167078","display_name":"Universitas Widyatama","ror":"https://ror.org/05v27w196","country_code":"ID","type":"education","lineage":["https://openalex.org/I4210167078"]}],"countries":["ID"],"is_corresponding":false,"raw_author_name":"Arief Rahmana","raw_affiliation_strings":["Universitas Widyatama Bandung"],"raw_orcid":null,"affiliations":[{"raw_affiliation_string":"Universitas Widyatama Bandung","institution_ids":["https://openalex.org/I4210167078"]}]}],"institutions":[],"countries_distinct_count":1,"institutions_distinct_count":1,"corresponding_author_ids":[],"corresponding_institution_ids":["https://openalex.org/I4210167078"],"apc_list":null,"apc_paid":null,"fwci":0.0,"has_fulltext":false,"cited_by_count":0,"citation_normalized_percentile":{"value":0.0,"is_in_top_1_percent":false,"is_in_top_10_percent":false},"cited_by_percentile_year":null,"biblio":{"volume":"5","issue":"3","first_page":"155","last_page":"167"},"is_retracted":false,"is_paratext":false,"is_xpac":false,"primary_topic":{"id":"https://openalex.org/T12177","display_name":"Resource-Constrained Project Scheduling","score":0.9775000214576721,"subfield":{"id":"https://openalex.org/subfields/1803","display_name":"Management Science and Operations Research"},"field":{"id":"https://openalex.org/fields/18","display_name":"Decision Sciences"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}},"topics":[{"id":"https://openalex.org/T12177","display_name":"Resource-Constrained Project Scheduling","score":0.9775000214576721,"subfield":{"id":"https://openalex.org/subfields/1803","display_name":"Management Science and Operations Research"},"field":{"id":"https://openalex.org/fields/18","display_name":"Decision Sciences"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}},{"id":"https://openalex.org/T10395","display_name":"Construction Project Management and Performance","score":0.021800000220537186,"subfield":{"id":"https://openalex.org/subfields/1803","display_name":"Management Science and Operations Research"},"field":{"id":"https://openalex.org/fields/18","display_name":"Decision Sciences"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}},{"id":"https://openalex.org/T13181","display_name":"Economic and Technological Systems Analysis","score":9.999999747378752e-05,"subfield":{"id":"https://openalex.org/subfields/1405","display_name":"Management of Technology and Innovation"},"field":{"id":"https://openalex.org/fields/14","display_name":"Business, Management and Accounting"},"domain":{"id":"https://openalex.org/domains/2","display_name":"Social Sciences"}}],"keywords":[{"id":"https://openalex.org/keywords/fiber-to-the-home","display_name":"fiber to the home","score":0.871999979019165},{"id":"https://openalex.org/keywords/project-scheduling","display_name":"project scheduling","score":0.7910000085830688},{"id":"https://openalex.org/keywords/schedule-control","display_name":"schedule control","score":0.9229999780654907},{"id":"https://openalex.org/keywords/pert","display_name":"PERT","score":0.699999988079071},{"id":"https://openalex.org/keywords/precedence-diagram-method","display_name":"precedence diagram method","score":0.8970000147819519},{"id":"https://openalex.org/keywords/critical-path","display_name":"critical path","score":0.9549999833106995},{"id":"https://openalex.org/keywords/project-delays","display_name":"project delays","score":0.6200000047683716},{"id":"https://openalex.org/keywords/microsoft-project","display_name":"Microsoft Project","score":0.7580000162124634},{"id":"https://openalex.org/keywords/project-planning","display_name":"project planning","score":0.43299999833106995}],"concepts":[{"id":"https://openalex.org/C68387754","wikidata":"https://www.wikidata.org/wiki/Q7271585","display_name":"Schedule","level":2,"score":0.6827999949455261},{"id":"https://openalex.org/C115874739","wikidata":"https://www.wikidata.org/wiki/Q825377","display_name":"Critical path method","level":2,"score":0.6635000109672546},{"id":"https://openalex.org/C58565012","wikidata":"https://www.wikidata.org/wiki/Q2112558","display_name":"Project planning","level":3,"score":0.5223000049591064},{"id":"https://openalex.org/C15952604","wikidata":"https://www.wikidata.org/wiki/Q179012","display_name":"Project management","level":2,"score":0.5008000135421753},{"id":"https://openalex.org/C112758219","wikidata":"https://www.wikidata.org/wiki/Q16038819","display_name":"Duration (music)","level":2,"score":0.48980000615119934},{"id":"https://openalex.org/C41008148","wikidata":"https://www.wikidata.org/wiki/Q21198","display_name":"Computer science","level":0,"score":0.48030000925064087},{"id":"https://openalex.org/C42475967","wikidata":"https://www.wikidata.org/wiki/Q194292","display_name":"Operations research","level":1,"score":0.4277999997138977},{"id":"https://openalex.org/C2775924081","wikidata":"https://www.wikidata.org/wiki/Q55608371","display_name":"Control (management)","level":2,"score":0.4104999899864197},{"id":"https://openalex.org/C127413603","wikidata":"https://www.wikidata.org/wiki/Q11023","display_name":"Engineering","level":0,"score":0.3928000032901764},{"id":"https://openalex.org/C201650216","wikidata":"https://www.wikidata.org/wiki/Q829492","display_name":"Procurement","level":2,"score":0.35440000891685486},{"id":"https://openalex.org/C21547014","wikidata":"https://www.wikidata.org/wiki/Q1423657","display_name":"Operations management","level":1,"score":0.35249999165534973},{"id":"https://openalex.org/C18762648","wikidata":"https://www.wikidata.org/wiki/Q42213","display_name":"Work (physics)","level":2,"score":0.3353999853134155},{"id":"https://openalex.org/C3019730874","wikidata":"https://www.wikidata.org/wiki/Q11272","display_name":"Microsoft excel","level":2,"score":0.3343999981880188},{"id":"https://openalex.org/C5395021","wikidata":"https://www.wikidata.org/wiki/Q1061410","display_name":"Program evaluation","level":2,"score":0.32359999418258667},{"id":"https://openalex.org/C60250085","wikidata":"https://www.wikidata.org/wiki/Q918141","display_name":"Work breakdown structure","level":5,"score":0.3206999897956848},{"id":"https://openalex.org/C133462117","wikidata":"https://www.wikidata.org/wiki/Q4929239","display_name":"Data collection","level":2,"score":0.3163999915122986},{"id":"https://openalex.org/C117110933","wikidata":"https://www.wikidata.org/wiki/Q811501","display_name":"Construction management","level":2,"score":0.30869999527931213},{"id":"https://openalex.org/C2777205345","wikidata":"https://www.wikidata.org/wiki/Q1454317","display_name":"Project team","level":2,"score":0.3068000078201294},{"id":"https://openalex.org/C2777719784","wikidata":"https://www.wikidata.org/wiki/Q7249400","display_name":"Project engineering","level":2,"score":0.30000001192092896},{"id":"https://openalex.org/C153185123","wikidata":"https://www.wikidata.org/wiki/Q1391624","display_name":"Sequence diagram","level":4,"score":0.2939000129699707},{"id":"https://openalex.org/C40919944","wikidata":"https://www.wikidata.org/wiki/Q947779","display_name":"Software project management","level":5,"score":0.2915000021457672},{"id":"https://openalex.org/C22212356","wikidata":"https://www.wikidata.org/wiki/Q775325","display_name":"Transport engineering","level":1,"score":0.27630001306533813},{"id":"https://openalex.org/C110354214","wikidata":"https://www.wikidata.org/wiki/Q6314146","display_name":"Engineering management","level":1,"score":0.2759999930858612},{"id":"https://openalex.org/C201995342","wikidata":"https://www.wikidata.org/wiki/Q682496","display_name":"Systems engineering","level":1,"score":0.262800008058548}],"mesh":[],"locations_count":1,"locations":[{"id":"doi:10.55606/jtmei.v5i3.6386","doi":"https://doi.org/10.55606/jtmei.v5i3.6386","is_oa":true,"landing_page_url":"https://doi.org/10.55606/jtmei.v5i3.6386","pdf_url":null,"source":{"id":"https://openalex.org/S4387284260","display_name":"JURNAL TEKNIK MESIN INDUSTRI ELEKTRO DAN INFORMATIKA","issn_l":"2963-7805","issn":["2963-7805","2963-8208"],"is_oa":false,"is_in_doaj":false,"is_core":false,"listed_in":[],"host_organization":null,"host_organization_name":null,"host_organization_lineage":[],"host_organization_lineage_names":[],"type":"journal"},"license":"cc-by-sa","license_id":"https://openalex.org/licenses/cc-by-sa","version":"publishedVersion","is_accepted":true,"is_published":true,"raw_source_name":"Jurnal Teknik Mesin, Industri, Elektro dan Informatika","raw_type":"journal-article"}],"best_oa_location":{"id":"doi:10.55606/jtmei.v5i3.6386","doi":"https://doi.org/10.55606/jtmei.v5i3.6386","is_oa":true,"landing_page_url":"https://doi.org/10.55606/jtmei.v5i3.6386","pdf_url":null,"source":{"id":"https://openalex.org/S4387284260","display_name":"JURNAL TEKNIK MESIN INDUSTRI ELEKTRO DAN INFORMATIKA","issn_l":"2963-7805","issn":["2963-7805","2963-8208"],"is_oa":false,"is_in_doaj":false,"is_core":false,"listed_in":[],"host_organization":null,"host_organization_name":null,"host_organization_lineage":[],"host_organization_lineage_names":[],"type":"journal"},"license":"cc-by-sa","license_id":"https://openalex.org/licenses/cc-by-sa","version":"publishedVersion","is_accepted":true,"is_published":true,"raw_source_name":"Jurnal Teknik Mesin, Industri, Elektro dan Informatika","raw_type":"journal-article"},"sustainable_development_goals":[{"id":"https://metadata.un.org/sdg/9","display_name":"Industry, innovation and infrastructure","score":0.7207000255584717}],"study_designs":[],"awards":[],"funders":[],"has_content":{"pdf":false,"grobid_xml":false},"content_urls":null,"referenced_works_count":0,"referenced_works":[],"related_works":["https://openalex.org/W2980115206","https://openalex.org/W3111404225","https://openalex.org/W7218115727","https://openalex.org/W3099217221","https://openalex.org/W3132133505","https://openalex.org/W7203669026","https://openalex.org/W2938030789","https://openalex.org/W7215386994","https://openalex.org/W3140151795","https://openalex.org/W4408476781"],"abstract_inverted_index":{"Fiber":[0],"To":[1],"The":[2,148],"Home":[3],"(FTTH)":[4],"network":[5],"construction":[6],"projects":[7],"require":[8],"effective":[9,191],"planning":[10],"and":[11,31,66,84,87,100,104,129,144,155],"schedule":[12,65,94],"control":[13,95],"to":[14,55,59,73],"ensure":[15],"completion":[16,47,172],"within":[17],"target":[18],"timeframes.":[19],"PT":[20],"XYZ,":[21],"a":[22,63,89,114],"company":[23,136],"specializing":[24],"in":[25,35,39,48],"the":[26,60,75,81,97,153,170,175,181,185],"procurement":[27],"of":[28,62,77,163,177,184],"telecommunications":[29],"goods":[30],"services,":[32],"experienced":[33],"delays":[34],"an":[36,159],"FTTH":[37],"project":[38,43,85,130,146,161,186,192],"West":[40],"Sumatra.":[41],"A":[42,109],"originally":[44],"scheduled":[45],"for":[46,93],"two":[49],"months":[50,57],"was":[51,118],"delayed":[52],"by":[53],"up":[54],"four":[56],"due":[58],"lack":[61],"structured":[64],"suboptimal":[67],"time":[68,193],"control.":[69,194],"This":[70],"study":[71,116],"aims":[72],"determine":[74],"sequence":[76],"work":[78],"activities,":[79],"identify":[80],"critical":[82],"path":[83],"duration,":[86],"establish":[88],"more":[90,190],"systematic":[91,182],"basis":[92],"using":[96],"Program":[98],"Evaluation":[99],"Review":[101],"Technique":[102],"(PERT)":[103],"Precedence":[105],"Diagram":[106],"Method":[107],"(PDM).":[108],"quantitative":[110],"descriptive":[111],"approach":[112],"utilizing":[113],"case":[115],"method":[117],"employed.":[119],"Data":[120],"were":[121],"gathered":[122],"through":[123],"interviews":[124],"with":[125],"field":[126],"supervisors,":[127],"technicians,":[128],"coordinators,":[131],"as":[132,134,139],"well":[133],"from":[135],"documents":[137],"such":[138],"progress":[140],"reports,":[141],"working":[142],"drawings,":[143],"technical":[145],"data.":[147],"results":[149],"indicate":[150],"that":[151],"applying":[152],"PERT":[154],"PDM":[156],"methods":[157],"yields":[158],"estimated":[160],"duration":[162],"41":[164],"days,":[165],"which":[166],"is":[167],"faster":[168],"than":[169],"two-month":[171],"target.":[173],"Furthermore,":[174],"use":[176],"Microsoft":[178],"Project":[179],"enables":[180],"visualization":[183],"schedule,":[187],"thereby":[188],"facilitating":[189]},"counts_by_year":[],"updated_date":"2026-10-28T10:33:24.094632","created_date":"2026-08-20T00:00:00"}